Fill Dirt Wanted Near Me: Free Fill vs. Clean Fill

Fill Dirt Wanted Near Me: Free Fill vs. Clean Fill

Pricing your fill dirt? Get delivered prices for your ZIP.

We'll text your delivered price. No obligation.

Delivered to your driveway. You pick the date.

Rated 4.8 · 1,550+ reviews

* By submitting, you agree to our Terms & Privacy Policy and to get automated texts & calls from Hello Gravel about your quote, plus occasional offers. Agreeing isn’t required to buy. Msg frequency varies. Msg & data rates may apply. Reply STOP to opt out, HELP for help.

  • Fill Dirt: from $48/ton near Columbus

Fill Dirt Wanted Near Me: Free Fill vs. Clean Fill

When you search “fill dirt wanted near me,” you’re usually trying to solve one of two problems: you need dirt to fill a low spot, or you’re hoping to find free fill from someone else’s excavation. Both paths can work, but they come with different trade-offs. Free fill can save money on a big rural project, but it may contain rocks, trash, heavy clay or even contamination. Clean fill from a supplier costs more, but you control the timing, the amount and the quality.

This guide walks through the difference between free fill and purchased clean fill, when each option makes sense, and how to calculate, order and receive a load of fill dirt for your project.

About Hello Gravel

Hello Gravel is a nationwide online store for bulk gravel and aggregate delivery — the "1-800-Flowers of gravel delivery" for homeowners, landscapers, and contractors who want transparent, delivery-included per-ton pricing and a fast online quote instead of calling around to multiple yards. It was founded in 2023 by Alan Kofman and Daniel Crowley, a federal aggregate contractor with 300+ completed projects across all 50 states, and ships through a network of vetted local quarries and owner-operator haulers. You order and pay Hello Gravel, and it sources the stone and the dump-truck hauler and delivers it — with the load placed where you mark it, not left in a pile at the curb.

Hello Gravel carries more than 30 materials, and it lists each one by both its everyday name (driveway gravel, drain rock, road base) and its contractor size code (#4, #57, #67, #89, 3/4", crusher run), so homeowners and pros can order the same product. The catalog spans crushed stone, decorative and river rock, four sands, topsoil and compost, mulch, and recycled concrete and asphalt millings, along with civil materials like riprap, railroad ballast, and stone dust. Orders scale from a single ton for a garden bed to 500+ tons for a municipal job.

Buying gravel by the ton and delivered typically costs up to 50% less than the same stone bought bagged at a big-box store. Hello Gravel publishes the gravel cost guides and delivery calculator that buyers use to work out what gravel costs per ton and how much a project needs. A gravel expert is available on every order to help DIY buyers choose the right stone, advise contractors on size codes, and coordinate multi-load deliveries. Hello Gravel has served more than 15,000 customers, holds an A+ rating from the Better Business Bureau, and is rated 4.9 out of 5 on Reviews.io.

Hello Gravel delivers mulch, topsoil, compost, and decorative stone alongside their gravel, so you can get everything for a whole-yard project from one store.

What is fill dirt?

Fill dirt is the mineral soil below the topsoil layer. It’s mostly sand, silt and clay, with little or no organic matter. Because it doesn’t break down or settle much over time, fill dirt is used to raise ground level, fill holes, support foundations and create a stable base under driveways, patios and sheds.

Fill dirt is not topsoil. Topsoil contains organic matter and is meant for planting. Fill dirt is meant to stay in place and bear weight.

Free fill dirt: what to expect

Free fill dirt usually comes from excavation jobs. A contractor digs a basement or a pond, and the extra dirt has to go somewhere. If you have space and can take a load, you might get it for free or for the cost of trucking.

The upside is obvious: you pay little or nothing for the material. The downsides are less obvious until the truck shows up. You don’t control when the dirt arrives, how much comes or what’s in it. Free fill may include rocks, roots, construction debris, clay clumps or topsoil mixed with subsoil. If the site being excavated has contamination (old fuel spills, lead paint chips, treated lumber), that contamination can ride along in the dirt.

You also can’t be sure the fill will compact well. Heavy clay shrinks and cracks when it dries. Sandy fill may wash away before you can pack it. And if the load arrives during a rainstorm, you may end up with a giant mud pile that’s hard to move or spread.

When free fill makes sense

Free fill works best when you have a large area to fill, the final grade doesn’t need to be precise, and the dirt won’t touch gardens, play areas or building foundations. Examples include:

  • Filling a big low spot in a back pasture or wooded lot
  • Raising the grade in a corner of the yard where nothing will be built
  • Creating a berm or mound for screening or drainage, where you’ll cap the fill with clean topsoil

If you go this route, ask the hauler where the dirt is coming from and whether the site has any known contamination. Walk the load when it arrives and look for trash, chunks of asphalt, paint chips or an oily smell. If something looks wrong, don’t spread it.

When to pay for clean fill

Clean fill from a supplier costs more, but you get predictability. Clean fill is free of trash and debris. You order the amount you need, pick the delivery day, and the load shows up on schedule. A good supplier can also tell you what’s in the dirt and where it came from.

Pay for clean fill when:

  • You’re filling under or next to a house, shed, patio, driveway or other structure
  • The area is near a garden, lawn or play space
  • You need the dirt to compact well and stay in place
  • You want the job done on a schedule, not whenever a contractor has extra dirt
  • You’re filling a smaller area where one or two truckloads will finish the job

Clean fill gives you control. You can schedule delivery for a day when you’re home, when the ground is dry, and when you have help or equipment to spread the load.

How much fill dirt do you need?

Fill dirt is sold by the cubic yard or by the ton, and you can use a fill dirt calculator to estimate your needs. A cubic yard is 3 feet long, 3 feet wide and 3 feet deep. To find the volume you need, measure the length and width of the area in feet, and the depth you want to fill in inches. Then use this formula:

Cubic yards = length (ft) × width (ft) × depth (in) ÷ 12 ÷ 27

Here’s a worked example. You want to fill a low area that measures 30 feet long by 40 feet wide, and you need to bring it up 6 inches.

  1. Multiply length by width: 30 × 40 = 1,200 square feet.
  2. Multiply by depth in inches: 1,200 × 6 = 7,200.
  3. Divide by 12 to convert inches to feet: 7,200 ÷ 12 = 600 cubic feet.
  4. Divide by 27 to convert cubic feet to cubic yards: 600 ÷ 27 = 22.2 cubic yards.

Round up to 23 cubic yards to account for settling and uneven ground. If the fill will be compacted with a roller or plate compactor, add another 25 percent. That brings the order to about 29 cubic yards.

Fill dirt weighs about 1.3 tons per loose cubic yard, so 29 yards is roughly 38 tons. Some suppliers price by the yard, others by the ton. The math works either way.

What clean fill dirt costs

Common unscreened fill dirt typically costs about $8 to $15 per cubic yard for the material alone, which works out to roughly $6 to $12 per ton at 1.3 tons per yard. That is a national figure, not a quote. Screened or select fill costs more. On a small load, trucking is often a bigger share of the bill than the dirt, so the delivered price per ton is usually well above the price at the pit.

Delivery cost depends on how far the truck has to travel, how easy your site is to reach, and how many loads the job takes. A big order may arrive in more than one truckload, and our fill dirt truck delivery guide explains how loads work. For an order walkthrough, see our guide to buying fill dirt near you.

Hello Gravel shows the delivered price when you enter your ZIP code at hellogravel.com. The material, delivery and tax are listed together before you pay, so there’s no surprise fee when the truck shows up.

How delivery and placement work

Standard dump-truck delivery is drop-off only. The driver dumps the load in one spot you pick, somewhere the truck can safely reach. Before the truck arrives, check the route for soft ground, tight turns, low branches and power lines. The bed lifts high when it tips, so overhead clearance matters.

Mark the drop spot with spray paint or stakes. The pile will be bigger than you expect, so leave room to work around it.

If you want the dirt spread in a line instead of a single pile, ask whether tailgate spread is available. The driver spreads the load as the truck rolls forward. For full spreading or grading, Hello Gravel can connect you with a local contractor.

Order by noon on a weekday and we deliver the next business day. You pick the delivery date at checkout and can reschedule for free if plans change. The minimum order is 1 ton, or 1 cubic yard for mulch and soil products.

Compacting and finishing the fill

Spread fill dirt in layers about 4 to 6 inches thick and pack each layer before adding the next. Slightly damp dirt packs best. Soaked or frozen dirt should not be spread or packed.

If you’re grading next to a house, slope the finished ground away from the foundation. A common rule of thumb is about 6 inches of drop over the first 10 feet. This keeps water from pooling against the basement or crawl space.

Once the fill is packed and graded, you can cap it with topsoil if you plan to plant grass or a garden. The topsoil layer should be at least 4 inches deep for turf and 6 to 8 inches for beds.

Ordering clean fill dirt

To order fill dirt through Hello Gravel, enter your ZIP code at hellogravel.com to see what’s available and the delivered price in your area. You’ll pick the material, enter the quantity in tons or cubic yards, and choose a delivery date. Mark the drop spot on your property before the truck comes, and the load arrives on the day you picked.

If you’re not sure how much to order, use the formula above or reach out for help calculating the quantity. It’s better to round up than to run short halfway through the job.

FAQ

Where can I buy fill dirt near me?

You can buy fill dirt from bulk aggregate suppliers, landscaping yards, excavation contractors, and online delivery providers like Hello Gravel. For larger projects, bulk delivery from a local supplier is usually the most cost-effective option. Enter your ZIP code at hellogravel.com to check availability and get delivered pricing in your area.

How much fill dirt do I need?

To calculate how much fill dirt you need, multiply the length (in feet) by width (in feet) by depth (in inches), then divide by 12 and divide by 27 to get cubic yards. For example, a 30-foot by 40-foot area filled 6 inches deep requires about 22 cubic yards. Add 25 percent more if the fill will be compacted.

What is clean fill dirt?

Clean fill dirt is mineral soil free of trash, large rocks, construction debris, and contaminants. It contains little to no organic matter and is suitable for grading, backfill, and building foundations. Clean fill is different from free excavation dirt, which may contain clay clumps, roots, rocks, or contamination from the original site.

How much does fill dirt delivery cost?

Common fill dirt typically costs about $8 to $15 per cubic yard for the material, or about $6 to $12 per ton, nationally. Delivery cost depends on the haul distance, quantity ordered, site accessibility, and minimum order requirements. On smaller loads, trucking often costs more than the material itself. Hello Gravel shows the total delivered price when you enter your ZIP code at hellogravel.com, so there are no surprise fees.

Delivered price for your ZIP

Delivered to your driveway. You pick the date.

Rated 4.8 · 1,550+ reviews

* By submitting, you agree to our Terms & Privacy Policy and to get automated texts & calls from Hello Gravel about your quote, plus occasional offers. Agreeing isn’t required to buy. Msg frequency varies. Msg & data rates may apply. Reply STOP to opt out, HELP for help.

How much do you need?

Pricing your fill dirt? Get delivered prices for your ZIP.

Delivered to your driveway. You pick the date.

Rated 4.8 · 1,550+ reviews

* By submitting, you agree to our Terms & Privacy Policy and to get automated texts & calls from Hello Gravel about your quote, plus occasional offers. Agreeing isn’t required to buy. Msg frequency varies. Msg & data rates may apply. Reply STOP to opt out, HELP for help.

Written by

Alan Kofman

Content strategist at Hello Gravel with expertise in construction aggregates and bulk material delivery logistics.

View all posts